NEWS
AWS data centre at Tigery: why France’s public-debate commission cannot be made to step in
Opponents of a planned Amazon Web Services data centre at Tigery, south of Paris, want a public debate. French law does not require one: data centres are not on the CNDP’s list, and a decree of 2 March 2026 closed the grid-connection route. The public’s real say will come during the environmental permit.

In brief
- Data centres are not among the projects that must be referred to the CNDP, France’s National Commission for Public Debate; the Campus IA at Fouju only had CNDP guarantors because its backers asked for them.
- Decree No. 2026-146 of 2 March 2026 took underground power lines out of the CNDP’s remit and removed substations of 63 kV or more from case-by-case environmental screening.
- An October 2025 opinion on Tigery’s local plan already flags 10.11 hectares of wetlands and unstudied waste heat, points that can be raised in a three-month consultation if AWS applies for an environmental permit.
On 4 November 2026 the mayor of Tigery, Germain Dupont, posted a video answering rumours about an Amazon Web Services (AWS) data centre planned on the town’s former Société Générale computer centre, according to the town’s own website and Les Echos. Opponents want a public debate. French law makes that very hard to obtain, and the reasons apply to any data centre in France.
What is planned at Tigery, and who is asking for a debate?
Tigery is a town in the Essonne département, south of Paris, on the edge of the Sénart forest (Les Echos). The site in question is the former data centre of the bank Société Générale. The town hall describes the project as an AWS data centre planned on that site, in a short post dated 4 November (Ville de Tigery).
Les Echos, in a piece published on 5 November 2026, describes the mayor as an independent with no party label, trying to reassure residents about the environmental impact. Opponents are calling for a public debate on a project that is still being examined and whose outline remains unclear, the paper reports (Les Echos). Two days later, Le Parisien reported that the location next to the forest has revived fears of wildfires.
No size, power demand or investment figure for Tigery appears in any of these sources. That gap matters for what follows.
Why can’t the CNDP simply be asked to hold a public debate?
The CNDP, or Commission nationale du débat public, is France’s National Commission for Public Debate. Its English-language pages describe it as an independent administrative authority since 2002, created to organise public participation early, while a project can still be reconsidered (CNDP). The law does not allow it to take up a case on its own initiative: a project has to be referred to it, most often by the developer (CNDP). Referral is mandatory only for the categories of projects listed in the table of Article R. 121-2 of the French Environment Code, the same table the March 2026 decree amends (Légifrance).
Data centres are not on that list. The commission says so in writing on its page for the Campus IA at Fouju, in the neighbouring Seine-et-Marne département: data centres do not count as “industrial facilities”, because a network of computers and storage needing air conditioning and cooling is not an industrial activity (our translation, CNDP). Fouju is a project put at €35 billion, with an estimated power need of 1.4 GW, backed by MGX (an investment company from the United Arab Emirates), Bpifrance, Nvidia and Mistral AI, according to the same page.
Fouju did get a prior consultation overseen by CNDP guarantors, from 13 October to 23 November 2025. That happened only because its backers asked for guarantors voluntarily, under Article L. 121-17 of the Environment Code, the CNDP page states.
Citizens do have a right of initiative, but outside the list it is narrow. It covers projects that require an environmental assessment and receive at least €5 million in public investment subsidies (CNDP). Whether any public money goes into Tigery is not known.
The CNDP list is a French layer. The EU baseline is Directive 2011/92/EU on environmental impact assessment, which the March 2026 decree itself cites. Under its Article 6(4), the public concerned must be given “early and effective opportunities” to take part in the decision while all options are open (EUR-Lex). It does not require a national debate commission. Each member state decides how that participation is organised, which is why the French route described here will not carry over to another country.
What did the decree of 2 March 2026 change, and from when?
There used to be an indirect route: the grid connection. A line of 400 kV or more and longer than 10 km triggered mandatory referral to the CNDP, whether it ran overhead or underground, as the law firm Adden explains in its analysis of the decree. Large data centres need very high voltage. At Fouju, the site is to be connected to the 400,000-volt line that passes over the plot, through a substation built on site by RTE, the French grid operator (CNDP).
Decree No. 2026-146, published in the Journal officiel (France’s official gazette) on 3 March 2026, inserts one word into that criterion: the length must now be “aérienne”, overhead. Underground lines leave the CNDP’s remit for every project not yet referred to it when the decree took effect on 4 March 2026. During the public consultation on the draft, from 8 to 30 September 2025, the CNDP itself objected that the change could take data centre connections out of its remit, according to the Adden analysis. The government’s answer stressed that underground lines have no significant environmental effects, the firm adds.
EU law draws a similar line. Annex I of the EIA Directive makes an assessment mandatory for overhead power lines of 220 kV or more and longer than 15 km, and Annex II leaves the transmission of electricity by overhead cables to national screening (EUR-Lex).
Article 2 of the French decree goes further. It deletes substations of 63 kV or more from heading 32 of the table annexed to Article R. 122-2, the list of projects screened case by case for an environmental assessment (Légifrance). A data centre can include one. At Villeneuve-Saint-Georges, in the Val-de-Marne, the regional environmental authority relied in its opinion of 2 May 2024 on heading 32 for a 225 kV substation. It also relied on heading 1 (classified installations burning more than 50 MW, here 321 MWth for each of the two data centres) and heading 39 (works on more than ten hectares, here 11.3) (MRAe Île-de-France).
The substation alone no longer triggers screening. Backup generators and site size, the other two headings used at Villeneuve-Saint-Georges, still can.
Running a small business near the site: where do you get a say?
A firm in the Sénart area, a shop, a contractor or a farm, has three openings, all of them procedural.
The first is the environmental permit. If the project needs an environmental authorisation, the public has been able to take part since 22 October 2024 for three months from the start of the procedure, rather than thirty days at the end, overseen by an independent inquiry commissioner (commissaire enquêteur), with access to all the opinions issued and two public meetings attended by the developer, according to the French Ministry for the Ecological Transition. The ministry presents the reform as an application of the Green Industry Act of 23 October 2023, and speaks of “the public” without limiting it to residents. On 15 November 2026, the Essonne prefecture’s page of public inquiries on classified installations listed no Tigery application (Préfecture de l’Essonne). That page and the regional environmental authority’s website are where an application and its opinion would appear.
The second is the file that already exists. The MRAe, the regional environmental authority for Île-de-France, reviewed the revision of Tigery’s local urban plan (PLU), which creates a “Rue des Vignes” zone to host a new data centre on land that is already built over. In its opinion APPIF-2025-105 of 15 October 2025, it noted 10.11 hectares of wetlands on that sector, identified by surveys in August 2023, which the plan does not protect (MRAe). It also found the file vague on how the future centre will be cooled. The file did not study recovery of its waste heat, even though the French law of 15 November 2021 on the environmental footprint of digital technology requires a data centre to reuse it or meet an efficiency indicator. Nor did it say whether a dedicated electrical connection would be needed. The public inquiry on the plan ran from 20 December 2025 to 20 January 2026 (Ville de Tigery).
Those points travel beyond France. Article 26(6) of the Energy Efficiency Directive (EU) 2023/1791 requires data centres with a total rated energy input above 1 MW to use their waste heat unless they show it is not technically or economically feasible. Article 12 of the same directive makes centres of 500 kW or more report energy data every year, though the European database is public only in aggregate, as covered in our piece on OpenAI’s water and power pledge.
The third is a voluntary concertation. Nothing stops the town council, the local authority grouping or associations from publicly asking AWS to request CNDP guarantors, as the Campus IA backers did. One limit applies to businesses. Where a citizens’ petition is possible, the CNDP counts adult EU nationals living in the area, 20% of the population within the project’s perimeter or 10% of the département or region (CNDP). A company is not counted; its owner, as a resident, is.
What is still unknown?
The size of the Tigery project, its power demand, its cooling method and any public funding are not public in the sources read. Neither is the date of a permit application. Until one is filed, there is nothing to consult on. More on how EU rules reach AI infrastructure is in our AI Act timeline and in the Society & Law section.
Frequently asked questions
Can residents force a public debate on a data centre in France?
Not directly. Data centres are not on the list of projects that must go to the CNDP. Citizens can petition only for projects that need an environmental assessment and receive at least €5 million in public investment subsidies. The developer can still ask the CNDP for guarantors.
What did the French decree of 2 March 2026 change for data centres?
It does not name data centres. Mandatory CNDP referral for 400 kV lines now counts only overhead length, so underground connections fall outside it, and substations of 63 kV or more no longer trigger case-by-case screening. It has applied since 4 March 2026.
How does the public get a say on an environmental permit in France?
Since 22 October 2024, the public is consulted for three months from the start of the procedure, overseen by an independent inquiry commissioner, with access to the opinions issued and two public meetings, according to the French Ministry for the Ecological Transition.
Do EU rules require data centres to reuse their waste heat?
Under Article 26(6) of the Energy Efficiency Directive (EU) 2023/1791, data centres with a total rated energy input above 1 MW must use their waste heat unless they show it is not technically or economically feasible. France had its own obligation from a law of 15 November 2021.
Share this article
Primary sources
- Décret n° 2026-146 du 2 mars 2026 portant modification du régime relatif à l’évaluation environnementale et aux critères de saisine de la Commission nationale du débat public — Légifrance (Journal officiel), published 3 March 2026 · accessed on
- Datacenters et infrastructure de raccordement au réseau électrique (Campus IA) à Fouju — Commission nationale du débat public, published 15 July 2025 · accessed on
- Nous saisir : responsables de projet, citoyens, associations et élus — Commission nationale du débat public, published 23 September 2026 · accessed on
- Our history — Commission nationale du débat public (English version) · accessed on
- Avis délibéré sur le projet de PLU de Tigery (91) à l’occasion de sa révision, n° APPIF-2025-105 — Mission régionale d’autorité environnementale d’Île-de-France, published 15 October 2025 · accessed on
- Avis délibéré sur le projet de centre de données de Villeneuve-Saint-Georges (94) — Mission régionale d’autorité environnementale d’Île-de-France, published 2 May 2024 · accessed on
- Autorisation environnementale : une réforme pour réduire les délais et donner plus de place à la participation du public — Ministère de la Transition écologique, published 22 October 2024 · accessed on
- Révision n° 2 du PLU : dossier d’enquête publique — Ville de Tigery · accessed on
- Information : projet data center — Ville de Tigery, published 4 November 2026 · accessed on
- Installations classées : enquêtes publiques en cours — Préfecture de l’Essonne · accessed on
- Essonne : un projet de data center AWS anime le débat public — Les Echos, published 5 November 2026 · accessed on
- Prévu en lisière de forêt de Sénart, le futur data center d’Amazon ravive la crainte des incendies — Le Parisien, published 7 November 2026 · accessed on
- Décret n° 2026-146 du 2 mars 2026 : analyse (exclusion des lignes souterraines de la CNDP) — Adden Avocats (blog) · accessed on
- Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment — EUR-Lex (Official Journal of the European Union), published 13 December 2011 · accessed on
- Directive (EU) 2023/1791 of 13 September 2023 on energy efficiency (Articles 12 and 26) — EUR-Lex (Official Journal of the European Union), published 13 September 2023 · accessed on
An article by the Rédaction Société & Droit, published under the editorial direction of Bastien Hugon. Editorial method and use of AI