NEWS
OpenAI will publish data centre water and power by site; in the EU those figures stay confidential
On 5 November 2026 OpenAI pledged to publish water and electricity use for each future US compute campus it owns and operates. In the EU, any data centre of 500 kW or more already reports those figures every year, but the European database only shows them in aggregate.

In brief
- OpenAI’s National Community Compact promises, site by site: published water and electricity use, independent noise studies, construction plans, no NDAs imposed on public officials, and power paid for at full cost.
- In the EU, Directive 2023/1791 requires data centres of 500 kW or more to report energy and water every year; Delegated Regulation 2024/1364 keeps each centre’s data confidential and publishes only national and EU aggregates.
- The first EU reporting round covered 770 data centres, about 36% of those required to report. A public rating label per centre is expected in 2027, and a consultation on minimum standards is open until 14 December 2026.
In one sentence: OpenAI promises to publish, campus by campus, the water and electricity use of its future US data centres; in the EU, the same figures already go to a European database every year, and governments can see them, but a resident cannot look up the site next door.
On 5 November 2026 OpenAI published two documents: a National Community Compact, setting out what it commits to around its compute campuses, and a Compute Campus Policy Blueprint, the rules it wants US lawmakers to impose on the whole industry. It came two days after the midterm elections, in which voters backed restrictions or rejected pro-development measures in all but one of 41 local ballot measures on data centres across 10 states, according to CNBC and Ballotpedia. Le Latent compared these pledges with what EU law already requires from data centres in Europe. More coverage of AI regulation is in our Society section.
What OpenAI promises, and where
The commitments apply to “every future compute campus OpenAI owns and operates”, OpenAI writes in its announcement. The compact speaks of communities “across America” and does not mention Europe. Each campus will have its own local compact, with a common core:
- water: a plan for each campus, priority to closed-loop or low-water cooling, and public reporting of water use “by location”, in other words site by site;
- electricity: OpenAI says it will pay the full cost of the power and grid infrastructure it needs, provide financial assurances before major spending, and publish on-site electricity use, including electricity generated and consumed;
- neighbours: published construction plans (traffic, noise, lighting) and independent noise studies before operations begin, then every year;
- public officials: no non-disclosure agreements required, with only narrow exceptions for security information and trade secrets;
- jobs: a published hiring strategy and an annual report on hiring and apprenticeships.
OpenAI already cites sums: $80 million committed to community priorities in Effingham County, Georgia, and $40 million in Pike County, Ohio, according to the compact. In Effingham, its agreement with Georgia Power lets the utility cut the power it delivers to the campus by up to 1,000 megawatts at times of high demand, the announcement says. The blueprint asks lawmakers to turn such obligations into rules for every developer, arguing that voluntary commitments are only a starting point.
In the EU, reporting already exists; site-level publication does not
Under Article 12 of the Energy Efficiency Directive (EU) 2023/1791, member states must require owners and operators of data centres with installed IT power demand of at least 500 kW to make the information in Annex VII publicly available every year: name, owner, location, installed power and key performance indicators, including energy and water use, as the Commission report summarises. In practice, that information goes into a European database whose content is published only in aggregate form.
Delegated Regulation (EU) 2024/1364 of 14 March 2024 settled the point. Operators report the previous year’s figures every year, the first time by 15 September 2024 and then by 15 May, according to the Commission report. The database publishes aggregates by member state and for the EU, and the Commission and member states, which see every record, must keep individual data confidential under Article 5(5); the report itself was prepared from anonymised data for that reason. DG Energy describes the public side as an online dashboard of aggregated data, updated monthly.
France is a useful worked example of how a member state applies this. The rules sit in Articles L. 236-1 to L. 236-3 of the French Energy Code, with checks and penalties, and the French Ministry for the Ecological Transition states that the individual data submitted are not meant to be disclosed. Data centres account for 2.2% of French electricity consumption, and the French energy agency ADEME expects that figure to grow by a factor of 3.7 by 2035, according to the same ministry page. Other countries add their own layer: Germany sets its national reporting threshold at 300 kW, the Commission report notes.
| OpenAI, US campuses (compact of 5/11/2026) | EU data centres of 500 kW or more | |
|---|---|---|
| Who | future campuses OpenAI owns and operates | every operator above the 500 kW threshold |
| Water | published by site, with cooling method | reported yearly, confidential per site |
| Electricity | used and generated on site, published by site | reported yearly, confidential per site |
| Noise, construction | independent studies and published plans | not covered by EU reporting |
| What the public sees | OpenAI’s website, no date given | an aggregated dashboard; a label per centre expected in 2027 |
| Legal force | voluntary commitment | legal obligation, checks and penalties |
Sources: OpenAI compact, Commission report and DG Energy, read on 13 November 2026.
What the aggregated EU figures show
The Commission report of 21 September 2026 (COM(2026) 500) is the first assessment of the database. In the first reporting period, 770 data centres submitted data, around 36% of the estimated total required to report; six member states reported none. EU data centres consumed 68 TWh of electricity in 2024, a figure expected to reach 114 TWh by 2030, or 3.2% of EU electricity demand.
On water, the average water usage effectiveness (WUE, water supplied per MWh of IT energy) was 0.58 m³/MWh in 2024, ranging from 0.07 to 1.28 across member states, based on 458 data centres whose values were deemed reliable, according to the same report. Roughly half of reporting data centres exceed a recommended baseline of 1.5 for power usage effectiveness (PUE) and/or 0.4 for WUE. For the second period, the Commission says it has already received preliminary data from at least 30% more data centres.
Next step: a public rating label for each data centre
On the same day the Commission put forward a common rating scheme. It will cover individual data centres above 500 kW, with transparent information on the energy and water they actually use, and the first labels are expected in 2027, according to its announcement. The act is first subject to a two-month scrutiny period by the European Parliament and the Council. The report says the label’s indicators were chosen among those already reported “while also respecting confidentiality concerns”. It will be a rating, not necessarily the cubic metres and megawatt hours that OpenAI promises.
The Commission is also preparing minimum performance standards for data centres. The public consultation is open until 14 December 2026 and the proposal is planned for the second quarter of 2027, says the DG Energy page. These are the rules that could set limits on water and energy, not just reporting duties; for the wider EU rulebook on AI, see our EU AI Act timeline.
What it changes, for whom, what to do
If you are a local councillor, resident or campaigner facing a data centre project in Europe, OpenAI’s compact will not apply to you, but it gives you a list of questions a US operator has agreed to answer in public. An operator of a 500 kW-plus site already reports its energy and water every year: asking it to publish those figures for the site means asking for what it already sends to the authorities. On water, the blueprint is precise: separate the initial cooling-system fill from ongoing use, water withdrawn from water consumed, and estimates from measured data. For how public consultation works on such a project in France, see our case study of the AWS data centre at Tigery (in French).
If you want a say in EU rules, the Commission’s consultation on minimum standards is open to anyone until 14 December 2026, from the DG Energy page. Other live EU consumer files touching AI include the Digital Fairness Act proposal.
If you use ChatGPT in Europe, nothing changes: the compact is about US building sites. It does frame a debate Europe will have too, as the EU aims to triple its data centre capacity by 2035, according to the Commission. How your own data is handled is a separate question, covered in our guide to objecting to AI training on your personal data.
What we do not know yet
OpenAI gives no date for its first reports and no list of the campuses concerned. Data centres that partners build and run for it are not mentioned in the compact, which covers only campuses “owned and operated by OpenAI”. On the EU side, the rating scheme is not yet in force, and the exact content of the public label remains to be seen in 2027.
Frequently asked questions
How much water does a data centre use in Europe?
No figure is public for individual sites. Across the EU, the Commission reports an average water usage effectiveness of 0.58 m³ per MWh of IT energy in 2024, ranging from 0.07 to 1.28 by member state, based on 458 data centres with reliable data.
Which data centres must report energy and water use in the EU?
Those with installed IT power demand of at least 500 kW. They report to the European database every year under the Energy Efficiency Directive; some countries set lower national thresholds, such as 300 kW in Germany.
Do OpenAI’s commitments apply in Europe?
No. Both documents are about the United States and do not mention Europe. They cover future campuses that OpenAI owns and operates itself, not data centres built and run by its partners.
Share this article
Primary sources
- Setting a new standard for responsible AI infrastructure — OpenAI, published 5 November 2026 · accessed on
- OpenAI’s National Community Compact: Building With Communities, Not Just In Them — OpenAI, published 5 November 2026 · accessed on
- AI Infrastructure That Works for America: Our Compute Campus Policy Blueprint — OpenAI, published 5 November 2026 · accessed on
- Report from the Commission on the energy efficiency of data centres in the EU, COM(2026) 500 final — European Commission (Council register), published 21 September 2026 · accessed on
- Making data centres energy efficient thanks to a new EU rating system — European Commission, published 21 September 2026 · accessed on
- Energy performance of data centres — European Commission, DG Energy · accessed on
- Directive (EU) 2023/1791 of 13 September 2023 on energy efficiency (Article 12 and Annex VII) — EUR-Lex, published 13 September 2023 · accessed on
- Commission Delegated Regulation (EU) 2024/1364 of 14 March 2024 (European database on data centres) — EUR-Lex, published 14 March 2024 · accessed on
- Efficacité énergétique des centres de données (datacenters) — French Ministry for the Ecological Transition · accessed on
- OpenAI pledges to pay for data center power after election highlights AI concerns — CNBC, published 5 November 2026 · accessed on
An article by the Rédaction Société & Droit, published under the editorial direction of Bastien Hugon. Editorial method and use of AI